213 Main Street, Epping, NH 03042

PHASE I

$592,967.00 CONTRACT

$50,288.00 INCENTIVES

TAX EXEMPT LEASE PURCHASE

MIDDLE/HIGH & ELEMENTARY

  • LED lighting and controls

PHASE II

$301,750.00 CONTRACT

$15,000.00 INCENTIVES

TAX EXEMPT LEASE PURCHASE

ELEMENTARY

  • High efficiency propane boilers

PHASE III

$6.95M CONTRACT

$432,808.00 INCENTIVES

TAX EXEMPT LEASE PURCHASE

 

MIDDLE/HIGH SCHOOL

  • Building automation system
  • Door replacement
  • Window replacement
  • Building envelope improvements
  • VRF heat pumps
  • EPDM roof replacement
  • Ventilation equipment replacement
  • Additional classroom ventilation

SAU OFFICE

  • Building automation system
  • High-efficiency boiler plant
  • Domestic hot water system

ADDITIONAL SERVICES

EMC contributed funds to purchase a GPS enabled field/parking lot robotic painter, a new entrance sign for the Middle/High school, and additional ceiling tile replacement.